DocumentsStaff ReportJun 18, 2018Pages 87–88
Staff Report: West Shore Parkway Sewer Station Lift Construction Award
Engineering staff report recommending award of construction contract(s) for the West Shore Parkway sewer station lift works.
Key facts
- Project: West Shore Parkway Sewer Station Lift
- Department: Engineering
- Purpose: Construction contract award recommendation
2nd Floor · 877 Goldstream Avenue · Langford, BC Canada · V9B 2X8
T · 250-478-7882 F · 250-478-7864
Staff Report: West Shore Parkway Sewer Lift Station Construction Award
To
Council
Date:
June 18, 2018
Department:
Engineering
Subject:
West Shore Parkway Sewer Lift Station Construction Award
Background
The City has retained KWL Engineering to design the sewer lift station that is part of the West Shore Parkway completion project infrastructure grant. This is the last remaining item from this grant to complete the entire project.
The purpose of this report is to obtain Council approval to award the construction of the lift station.
Commentary
Staff anticipate that the tender documents for the West Shore Parkway sewer lift station will be ready late June/July. Staff intend to post the project to BC Bid in a fair and transparent tendering process pursuant to the City’s Purchasing Policy.
Staff are suggesting that Council allow award of the West Shore Parkway Sewer Lift Station Construction to the lowest compliant bidder and to fund the project through the West Shore Parkway Infrastructure Grant.
Financial Implications
This project is funded through the New Building Canada Infrastructure grant for the West Shore Parkway completion project.
Legal Implications
None noted. The lift station will be constructed on City land.
Options
That Council:
- Award the construction of the West Shore Parkway Sewer Lift Station to the lowest compliant bidder, so long as the bid is within budget, and fund the project from the New Building Canada Infrastructure grant for the West Shore Parkway Completion project;
OR - Not award the construction of the West Shore Parkway Sewer Lift Station
Respectfully submitted,
Submitted by:
Michelle Mahovlich, P.Eng, P.Geo, Director of Engineering
Concurrence:
Matthew Baldwin, MCIP, RPP Director of Planning
Concurrence:
Michael Dillabaugh, CPA, CA, Director of Finance
Concurrence:
Braden Hutchins, Director of Corporate Services
Concurrence:
Darren Kiedyk, Chief Administrative Officer
:mm