Impact of 2025 Budget on Reserve Funds

Projected reserve fund impacts for 2025 including contributions, interest, developer contributions, transfers and capital expenditures with resulting ending balances.

Key facts

  • Table header: City of Langford — Impact of 2025 Budget on Reserve Funds
  • Balance, end of year (aggregate reported): $29,823,338
  • Shows projected contributions from revenue and capital expenditures affecting reserve balances

Impact of 2025 Budget on Reserve Funds

City of Langford

Category Equipment Replacem't (C) Surplus Capital Works and Equipment (C) Sidewalk (C) Infrastructure Sustainability Reserve Parks and Open Space (C) Parkland Improvem't (C) General Amenity Afford. Housing Community Works (Gas Tax) Firehall #4 (C) Police Building Capital (C) Roads DCC (C) Storm Drain DCC (C) Park Land DCC (OLD) (C) Park Land DCC (NEW) (C) Park Impr. DCC (C) Total
Balance, beginning of year 911,340 2,122,711 416,357 66,871 1,331,435 3,034,072 104,243 2,267,949 4,106,647 2,285,489 1,765,535 0 128,099 229,383 169,746 262,413 652,421 19,854,709
Plus: Contributions from revenue 900,000 0 0 500,000 70,000 1,470,000
Plus: Interest earned 18,227 42,454 8,327 1,337 26,629 60,681 2,085 45,359 82,133 45,710 35,311 0 2,562 4,588 3,395 5,248 13,048 397,094
Plus: Sale of property 0
Plus: Developers' contributions 10,000 50,000 50,000 2,000,000 75,000 30,000 1,750,000 225,000 600,000 1,000,000 5,790,000
Plus: Other Contributions 500,000 1,405,000 1,373,532 4,683,532
Less: Contibution to Operating 0 -366,760 -1,701,985 -15,695 -120,000 -2,204,440
Transfer between funds -1,750,000 1,750,000
Transfer to Operating for Capital costs -1,250,000
Capital Expenditures -629,000 -305,000 0 0 0 0 -800,000 0 0 -70,000 0 0 -1,000,000 -425,000 -3,229,000
Balance, end of year 1,200,567 2,298,405 274,684 78,209 1,358,064 3,144,753 156,328 2,311,323 4,248,085 3,584,731 1,830,845 0 130,661 458,971 173,141 1,617,661 1,240,469 26,761,895
Page 46

Impact of 2026 Budget on Reserve Funds

City of Langford

Category Equipment Replacem't (C) Surplus Capital Works and Equipment (C) Sidewalk (C) Infrastructure Sustainability Reserve Parks and Open Space (C) Parkland Improvem't (C) General Amenity Afford. Housing Community Works (Gas Tax) Firehall #4 (C) Police Building Capital (C) Roads DCC (C) Storm Drain DCC (C) Park Land DCC (OLD) (C) Park Land DCC (NEW) (C) Park Impr. DCC (C) Total
Balance, beginning of year 1,200,567 2,298,405 274,684 78,209 1,358,064 3,144,753 156,328 2,311,323 4,248,085 3,584,731 1,830,845 0 130,661 458,971 173,141 1,617,661 1,240,469 24,106,895
Plus: Contributions from revenue 750,000 500,000 70,000 1,320,000
Plus: Interest earned 24,011 45,968 5,494 1,564 27,161 62,895 3,127 46,226 84,962 71,695 36,617 0 2,613 9,179 3,463 32,353 24,809 482,138
Plus: Sale of property 0
Plus: Developers' contributions 10,000 50,000 50,000 2,000,000 75,000 30,000 1,750,000 225,000 600,000 1,000,000 5,790,000
Plus: Other Contributions 500,000 1,405,000 1,905,000
Less: Contibution to Operating -300,000 0 -15,695 -120,000 -435,695
Transfer between funds -1,750,000 1,750,000
Transfer to Operating for Capital costs -750,000 -1,000,000
Capital Expenditures -1,175,000 -200,000 0 0 0 -800,000 -70,000 0 0 -1,000,000 -100,000 -3,345,000
Balance, end of year 799,578 2,544,373 735,177 89,773 1,385,225 3,257,648 209,454 3,057,549 4,392,351 3,536,425 1,897,462 0 133,274 693,150 176,604 3,000,014 2,165,279 29,823,338