This site is in beta — data may be incomplete and features are still being added.

MattersTransportationFirst seen Apr 18, 2016

Westshore Parkway Segment 8 contract

Approved

The work adds a left-turn lane from the Trans-Canada Highway to Westshore Parkway, with related lane, intersection and traffic-signal improvements. Development charges and a federal infrastructure grant fund the project.

Where it stands: Staff were directed to award the contract to the lowest compliant bidder Apr 18, 2016.

Background

Earlier and later steps of the same initiative.

  1. Sep 5, 2017 – Sep 18, 2017

    West Shore Parkway road closure

    The proposal would close and dispose of part of West Shore Parkway as part of the Parkway completion project, through a land exchange with Glenshire Industrial Park Inc. Closing part of the route could affect access while enabling the project to proceed.

Timeline

Every time this matter appeared in council records, newest first.

  1. April 18, 2016· Council

    Staff directed to award Segment 8 construction contract

    Council directed staff to award the construction contract for Segment 8 of the West Shore Parkway to the lowest compliant bidder, funded from Development Cost Charges and the New Building Canada Infrastructure Fund.

    Decision: Directed staff to award Westshore Parkway Segment 8 contract to the lowest compliant bidder.

    Passed