BYLAW NO. 1848 — 'City of Langford Development Procedures, Amendment Bylaw No. 19, 2019' (FIRST, SECOND AND THIRD READINGS)
Bylaw No.1848 to amend City of Langford Development Procedures presented for first, second and third readings.
Key facts
- Bylaw No.: 1848
- Title: City of Langford Development Procedures, Amendment Bylaw No. 19, 2019
- Procedure: FIRST, SECOND AND THIRD READINGS (agenda page 159)
2nd Floor · 877 Goldstream Avenue · Langford, BC Canada · V9B 2X8
T · 250-478-7882 F · 250-478-7864
Staff Report to Council
Date:
May 21, 2019
Department:
Planning
Subject:
Bylaw Nos 1848, 1849, and 1850 - Planning, Subdivision and Building Application Fee Adjustments
Background
At their Regular meeting held May 6th, 2019, Council adopted Bylaw No 1838 to approve the 2019 Tax Rate, which includes an increase of 2.49%.
Commentary
As has occurred in previous years, staff have prepared bylaws to amend the Building, Planning and Subdivision related fees commensurate with the general tax increase. As such, Bylaw No 1848 has been drafted to adjust the following fees by 2.49%:
- OCP amendment applications;
- Rezoning applications;
- Public Hearings;
- Development Permit and Development Permit amendment applications;
- Development Variance Permit applications;
- Letters of exemption;
- Temporary Use Permit applications;
- Board of Variance applications;
In addition to these fee adjustments, staff have included some minor changes to the Planning fee schedule in this bylaw, including:
- Removing obsolete fees;
- Updating inconsistencies in the commercial, industrial, and business park form and character Development Permit fee categories; and
- Clarifying wording in the Development Permit Amendment categories.
Bylaw No 1849 includes a 2.49% fee adjustment to Subdivision related fees as well as adjustments to the administration fee and per lot unit fees collected at the initial and final stages of the application process. The administration fee has been increased to better reflect basic staff time required regardless of application size at these steps in the process, and the per-unit multiplier has been reduced to offset this increase somewhat.
Bylaw No 1850 includes fee adjustments to Building Permit related fees.
Financial Implications
Generally increasing fees to keep up with the cost of living should maintain the relationship between applications and cost recovery, which Council is required to continue under Provincial legislation.
Legal Implications
None.
Options
That Council:
- Give first, second and third reading to Bylaw No. 1848; and
- Give first, second and third reading to Bylaw No. 1849; and
- Give first, second and third reading to Bylaw No. 1850;
OR
- Take no action at this time with respect to adjusting application fees
Submitted by:
Leah Stohmann, MCIP, RPP, Deputy Director of Planning
Concurrence:
Adriana Proton, Manager of Legislative Services
Concurrence:
Matthew Baldwin, MCIP, RPP Director of Planning
Concurrence:
Michael Dillabaugh, CPA, CA, Director of Finance
Concurrence:
Braden Hutchins, Director of Corporate Services
Concurrence:
Darren Kiedyk, Chief Administrative Officer
:ls
CITY OF LANGFORD
BYLAW NO. 1848
A BYLAW TO AMEND BYLAW NO. 209, “DISTRICT OF LANGFORD DEVELOPMENT PROCEDURES, 1997”
The City of Langford Council in open meeting assembled enacts as follows:
- Bylaw No. 209, cited as “District of Langford Development Procedures, 1997” is amended by:
a) By replacing Schedule ‘D’ with the following:
"Official Community Plan Amendment Fees
| Application Type | Base Fee | Public Hearing | Combined Fee |
|---|---|---|---|
| Application concurrent with Application to Rezone | $2,294 | nil | $2,294 |
| All Land Uses <1000m2 of site area | $3,209 | $2,522 | $5,731 |
| All Land Uses 1001m2 – 8094m2 (2ac) of site area | $6,649 | $2,522 | $9,171 |
| All Land Uses >8094m2 – 40,467m2 (10ac) | $9,514 | $2,522 | $12,036 |
| All Land Uses >40,467m2 (10ac) | $11,808 | $2,522 | $14,330 |
Zoning Amendment Fees
| Application Type | Base Fee | Public Hearing | Combined Fee |
|---|---|---|---|
| Text amendment only, under existing zoning for changes to Density Bonusing provisions | $1033 | $2,522* | $3,555 |
| Text Amendment only under existing zoning for changes to not more than two (2) aspects of the Zoning Bylaw, other than Density Bonus provisions | $2,062 | $2,522* | $4,584 |
| All Land Uses <1000m2 of site area | $3,209 | $2,522* | $5,731 |
| All Land Uses 1001m2 – 8094m2 (2ac) of site area | $6,649 | $2,522* | $9,171 |
| All Land Uses >8094m2 – 40,467m2 (10ac) | $9,514 | $2,522* | $12,036 |
| All Land Uses >40,467m2 (10ac) | $11,808 | $2,522* | $14,330 |
*Fee reduced to $2,047 if public hearing waived
**Add $2,238 for the creation of a new zone designation"
b) By replacing Schedule ‘E’ with the following:
"Development Permit Fees
If any work for which a permit is required commences prior to a permit being issued, the fee payable shall be doubled.
Interface Fire Hazard Development Permit Area (ONLY) – Development Permit for one- and two-family residential development on an individual lot and/or the creation of not more than two lots by subdivision where development is fully compliant with Interface Fire Hazard design guidelines.
$287Riparian Development Permit Area (ONLY) – Development Permit for one- and two-family residential development on an individual lot where no work is occurring within a Streamside Protection and Enhancement Area (SPEA) as defined by a qualified professional;
$572Two-Family Residential (Duplex) - compliant with Design Guidelines and which may or may not include Interface Fire Hazard Development Permit Area;*
$917Two-Family Residential (Duplex) – not compliant with Design Guidelines and which may or may not include Interface Fire Hazard Development Permit Area and may or may not include variances;**
$2,350
For combined Environmentally Sensitive/Hazardous and Form & Character applications, fees shall be paid on the basis of the greater of either the Environmentally Sensitive/Hazardous Development Permit Area(s) Impacted (column A) OR the scale of development (column B)
| Column A (Environmentally Sensitive/Hazardous Development Permit Areas Impacted) | Column B (Form & Character) | Fee |
|---|---|---|
| Less than 150m2 of site area within a defined development permit area | Less than 100m2 of new commercial/industrial/business park GFA; and/or exterior renovation of existing intensive residential (including duplex) or multi-family residential buildings that represents a change to the form and character of a building or buildings; | $572 |
| 150-1000m2 of site area within a defined development permit area | Up to and including 4 residential units; and/or Up to 200m2 of new Com/Ind/Bus Park GFA; and/or exterior renovation of existing Com/Ind/Bus Park buildings up to 200m2 of GFA that represents a change to the form and character of a building or buildings; | $2,062 |
| 1001-4500m2 of site area within a defined development permit area | 5-12 residential units; and/or Up to 300 m2 of new Com/Ind/Bus Park GFA and/or Exterior renovation of existing Com/Ind/Bus Park buildings up 2000m2 of GFA that represents a change to the form and character of a building or buildings; | $4,357 |
| 4,501-25,000m2 of site area within a defined development permit area | 13-49 residential units; and/or Up to 4500 m2 of new Com/Ind/Bus Park GFA and/or exterior renovation of existing Com/Ind/Bus Park buildings over 2000m2 of GFA that represents a change to the form and character of a building or buildings; | $6,649 |
| >25,000m2 of DP site area | 50+ residential units; and/or 4501 m2+ of new Com/Ind/Bus Park GFA | $10,891 |
*A duplex development permit issued by Council’s delegate
**A duplex development permit issued by Council
Development Permit Amendment Fees
The Director of Planning may consider the following types of amendments to an issued Development Permit, where such changes maintain the overall intent of the previously issued Development Permit and are consistent with the Development Permit Area Guidelines appended to Zoning Bylaw No. 300
Minor amendment for changes that are eligible for a Development Permit Exemption in accordance with s.1.4 of Appendix A to Zoning Bylaw No. 300
No Fee, unless a Letter of Exemption is requested or requiredMinor amendment for changes that:
• Require the issuance of a Development Permit Amendment for the purpose of issuing a variance to reduce a bylaw requirement by no more than 10%
$229Moderate amendment for changes that:
• Require the issuance of a Development Permit Amendment for the purpose of:
• Increasing floor space by more than 10% of the GFA originally approved, but less than 20%;
• Issuing a variance to reduce a bylaw requirement by more than 10%;
• Adjusting a streamside protection and enhancement area per the conditions specified in s.2.3.4 of Appendix A to the Zoning Bylaw No. 300 and where such adjustment is supported by the project biologist
16% of the original feeMajor amendment for changes that are not considered to be a Minor or Moderate amendment
27% of the original feeAppeal Fee (if Development Permit cannot be issued by Council’s delegate)
$1,432 in addition to above feesDevelopment Permit Issued by Council with Variances (other than duplex)
$1,432 in addition to the above feesLetter of Exemption from the Requirements of a Development Permit
$115
Other Fees
Board of Variance
$715Counter Petition: If the City is required to provide a counter petition opportunity as a result of any planning related application (Official Community Plan Amendment, Rezoning, Development Permit, Development Variance Permit, and Temporary Use Permit).
$642
Development Variance Permit Fees
- Application Fee
$1,432
Temporary Use Permit Fees
Application Fee
$2,007Renewal Fee
$287 "
- This Bylaw may be cited for all purposes as "City of Langford Development Procedures, Amendment Bylaw No. 19, 2019, Bylaw No. 1848".
READ A FIRST TIME this day of , 2019.
READ A SECOND TIME this day of , 2019.
READ A THIRD TIME this day of , 2019.
ADOPTED this day of , 2019.
MAYOR