DocumentsStaff ReportJun 1, 2020Pages 31–34
Staff Report - Award of Peatt at Brock Roundabout Construction Contract
Report recommending award of the Peatt at Brock roundabout reconstruction contract to the lowest bidder to improve safety, pedestrian crossings and emergency vehicle movements.
Key facts
- Project funded from City Development Cost Charge (DCC) Bylaw No. 1700, 2017 (Project #12)
- Recommended contractor: CopCan Civil Ltd.
- Recommended contract amount: $447,675 (excluding GST)
- Tender advertised May 5, 2020; reconstruction staged (Larkhall leg deferred)
Staff Report - Award of Peatt at Brock Roundabout Construction Contract
Date:
June 1, 2020
Department:
Engineering
Background
The City tendered the reconstruction of the Peatt at Brock roundabout on May 5, 2020 on the publicly accessible BC Bid website.
The purpose of this report is to obtain Council approval to award this construction project.
Commentary
The City retained McElhanney Consulting to undertake the detailed design and tender of the Peatt at Brock roundabout reconstruction.
The reconstruction will be staged. This first part of the reconstruction will include:
- Three legs of the roundabout, north and southbound on Peatt road and westbound on Brock Road;
- Two improved pedestrian crossings (on Peatt north of Brock; on Brock west of Peatt), both with flashing pedestrian lights and pedestrian refuge islands;
- Improved movements for fire trucks and emergency response vehicles. Fire staff have been part of the drawing reviews for this project; and
- Support from ICBC for the safety improvements
The remaining Larkhall leg of the roundabout will be done at a future date when Larkhall will be expanded to include traffic in both directions. The timing of this stage is not known at this time.
A rendering of the current construction is provided as Figure 1.

This project was originally slated to tender in the Fall of 2020, for construction in the Spring of 2021. However with the current COVID-19 situation, tendering and awarding this project sooner than expected will aid in continuing the positive economic development in Langford.
Financial Implications
The Peatt at Brock roundabout construction project is part of the City of Langford Development Cost Charge Bylaw No. 1700, 2017 and is Project #12 in Schedule B of the bylaw. The project is funded by the City through the DCC program.
Bids Summary
McElhanney reviewed the bids for the project. A summary is provided below:
| Contractor | Bid | Any Comments |
|---|---|---|
| CopCan Civil Ltd | $447,675 | none |
| Scansa Construction Ltd. | $484,877 | none |
| Don Mann Excavating | $565,625 | Corrected price based on minor error in bid; did not affect the overall tender price ranking of the received tenders |
| Draycor Construction | $575,658 | none |
| G&E Contracting LP | $594,815 | none |
McElhanney is recommending that the contract to construct the Peatt at Brock roundabout be awarded to CopCan Civil Ltd. for the amount of $447,675 excluding GST.
Legal Implications
All of the works will take place within City owned road rights of way. The driveway for the home at 808 Brock Road has to be moved west to provide for a safer access/egress. Staff have worked with that homeowner to determine the most amenable plan for that work.
Options
That Council:
- Award the construction of the Peatt at Brock roundabout to CopCan Civil Ltd. for the amount of $447,675 excluding GST and fund the project from the City’s Development Cost Charge program; OR
- Not award the construction of the Peatt at Brock roundabout at this time.
Respectfully submitted,
Submitted by:
Michelle Mahovlich, P.Eng, P.Geo, Director of Engineering
Concurrence:
Adriana Proton, Manager of Legislative Services – email approval
Concurrence:
Matthew Baldwin, MCIP, RPP Director of Planning – email approval
Concurrence:
Chris Aubrey, Fire Chief – email approval
Concurrence:
Ivan Leung, P.Eng., Manager of Engineering Construction – email approval
Concurrence:
Michael Dillabaugh, CPA, CA, Director of Finance – email approval
Concurrence:
Braden Hutchins, Director of Corporate Services – email approval
Concurrence:
Darren Kiedyk, Chief Administrative Officer – email approval
:mm